|
| Our achievements to put it humbly, have been hailed by all Builders for they generally benefit all alike irrespective of the class or category they belong to. Some of these are listed below:- |
| a. |
The Contract conditions have been got amended for release of retention money (leaving an amount of Rs. 1.50 lakhs or 1% of contract, whichever is more) on completion of the work. |
| b. |
Payment for advance on account of materials collected at site is now made upto 85% in all contracts. The balance 15% amount of retention money can also be released against bank guarantee bonds in respect of contracts costing over Rs.50 lakhs. |
| c. |
The definition of ‘Accepted Risks’ earlier did not include invasion, act of foreign enemies, hostilities, rebellion, revolution, Military or usurped power and Acts of God such as lightning, unprecedented floods and tornado. These have now been brought within the scope of description of ‘Acceptable Risks’. |
| d. |
The provision in conditions of contracts regarding maintenance period of 12 months was often misused and mis-interpreted requiring Builders to undertake even normal items of maintenance arising out of fair, wear and tear. This is now avoided by change in terminology of said period from ‘ maintenance period’ to ‘defect liability period’. |
| e. |
The Government have agreed to issue mobilization advance for contracts of specialist works costing over Rs. one crore. |
| f. |
Most important amendments that have been carried out to term and conditions of the contract are escalation clauses for reimbursement in prices of materials and wages of labour. Earlier provision catered for reimbursement of increase in price in cost of materials was due to act of legislature only and there again cumbersome procedures were specified to be gone through in order to establish proof of payment. The subject conditions now inserted in contracts do away with such drills and provide for escalation in prices of materials on the All India Wholesale Price Indices or a formula based escalation in wages of labour on the basis of increase in minimum wages, which is a simplified method. |
| g. |
In view of the all round increase in prices of material and labour, the tendering limits of various classes of contractors have since been substantially raised from time to time. |
| h. |
The qualifications and experience of engineers necessary to be employed on works by the contractor in terms of the condition 25 of General Conditions of Contract have now been considerably relaxed. |
| i. |
The additional security is now to be released in two stages – 50% at the time of payment of the undisputed amount of the final bill and balance after the expiry of the ‘Defect Liability Period.’ |
| j. |
Department has agreed to reimburse tax/ levy imposed by Govt. after receipt of tender if the tax/ levy is directly payable to the Govt. |
| k. |
The policy of denying certain claims from arbitration has now been changed and all claims are now being referred to arbitrator who himself would decide whether a claim is arbitrable or not. |
| l. |
Amount of compensation for delay in completion has been reduced and a maximum limit laid down for compensation. |
| m. |
A new formula is evolved for RAR payment when contract is running under compensation. As per this formula, if total RAR amount exceeds the amount of maximum compensation, no amount is to be retained for retention money. |
| n. |
If there is delay in handing over the site as a result of which no work could commence, there is a provision of amending the work order postponing the date of commencement and completion. |
| o. |
In the case of deviations , percentage of overhead and profit has been enhanced from 10 to 15. We are stressing that even this enhancement is not adequate and should be made at least 25%. |
| p. |
There used to be delay in approving of yardstick resulting in delay in payment of RARs. The Department has now agreed to include yardsticks in tender documents in all lump sum tenders for common and standard buildings. |
| q. |
To avoid delay in release of Additional Security Deposit, it has been decided that FDRs for the same will be pledged in favour of Accepting Officers instead of Controller of Defence Accounts. |
| r. |
The limit of passing of final bills by UA’s without reference to CDA has been enhanced to Rs.2.5 lakhs. Efforts are on to get this limit increased further to at least Rs.15 lakhs. |
| s. |
To avoid hardship to Builders in getting material tested, it has been decided that a site laboratory for all contracts of Rs. 1 crore and above can be set up by the contractor for which suitable clause will be included in tenders. |
| t. |
It has been agreed to by the Department that the MES Builders Association of India is the only MES Builders Association recognized by the Ministry of Defence. Any other Association being not recognized should not be encouraged and no cognizance be given to them. |